TM 5-2410-233-23
VALVE MECHANISM MAINTENANCE
THIS WORK PACKAGE COVERS
Removal, Disassembly, Cleaning, Inspection, Assembly, Installation, Locating Top Dead Center (TDC) Compression
Stroke for Number 1 Piston, Adjusting Valve Clearance
INITIAL SETUP
Tools and Special Tools
Materials/Parts - Continued
Bolt, timing, 3/8 in. -16NC, 2 in. long
Tool kit, general mechanic's (Item 112, WP 0185 00)
O-ring (12)
Shop equipment, common no. 1 (Item 97, WP 0185
Pin (17)
Plug (18)
Materials/Parts
References
Cleaning compound, solvent (Item 4, WP 0184 00)
Compound, antiseize (Item 6, WP 0184 00)
Equipment Condition
OIl, lubricating (Item 24, WP 0184 00)
Valve mechanism cover removed (WP 0016 00)
Crankcase guard removed (WP 0129 00)
Tag, marker (Item 35, WP 0184 00)
REMOVAL
1.
Loosen 12 nuts (1) and adjustment screws (2) to have maximum valve clearances.
2.
Remove six capscrews (3) washers (4) from rear support bracket (5), four angle brackets (6) and eye bracket (7) that
secure rocker shaft (8).
3.
Remove rocker shaft (8) from cylinder head (9).
9
1
3
7
2
4
6
8
5
386-833-1
|