![]() TM 9-2320-363-20-2 
STE/ICE SHUNT REPLACEMENT 
This task covers: 
a. Removal 
b. Cleaning/Inspection 
c. Installation 
INITIAL SETUP I 
Applicable Configuration: 
Materials/Parts (Cont): 
M917A1 and M917A1 w/MCS 
Tags, IdentificationAppendix C, Item 26 
Tools and Special Equipment: 
Personnel Required: (2) 
Tool Kit, SC 5180-90-CL-N26 
Equipment Condition: 
Materials/Parts: 
Reference 
Condition Descripti on 
Nut, Lock (2) 
Page 2-29 
Batteries Disconnected 
Washer, Lock (2) 
REMOVAL 
NOTE 
Tag all wires and cables prior to removal to aid in installation. 
1. 
REMOVE TWO SCREWS (1), TWO LOCK WASHERS (2), THREE CABLES (3), AND TWO WIRES (4) FROM 
STE/ICE SHUNT (5). DISCARD LOCK WASHERS. 
2. 
REMOVE TWO SCREWS (6) AND TWO WIRES (7). 
3. 
REMOVE TWO LOCK NUTS (8), TWO WASHERS (9), TWO SCREWS (10), TWO WASHERS (11), AND STE/ICE 
SHUNT (5) FROM FRAME RAIL (12). DISCARD LOCK NUTS. 
 | 
| 
 