TM 5-2420-222-20-3
LOADER CONTROL VALVE HANDLE AND LINKAGE - CONTINUED
ACTION
LOCATION
ITEM
REMARKS
4.
Two spool devises
Two cotter pins (6)
a.
Using slip-joint pliers, straighten
(4) and two
ends and take out.
connector pins (5)
b.
Get rid of.
5.
Boom control rod
Two connector
Take out.
(7), bucket control
pins (5)
rod (8), and two
spool devises (4)
6.
Loader control box
Two screws (11) and
a.
Using 9/16-inch box wrench, unscrew
(9) and control
lockwashers (12)
and take out.
control pivot (10)
b.
Get rid of lockwashers (12).
7.
Loader control box
Control pivot (10)
Take off.
(9) and two spool
with assembled parts
clevises (4)
2-1325
|