TM 5-2420-222-20-3
LOADER CONTROL VALVE HANDLE AND LINKAGE
This task covers:
a. Removal (page 2-1324)
e.
Repair (page 2-1330)
b. Disassembly (page 2-1326)
f.
Assembly (page 2-1330)
c. Cleaning (page 2-1328)
g.
Installation (page 2-1334)
d. Inspection/Replacement (page 2-1329)
h.
Adjustment (page 2-1334)
INITIAL SETUP:
Tools
Materials/Parts - Continued
Gage, thickness
Pin, cotter, connector pin (two required)
Hammer, ball-peen, 1-pound head
Pin, cotter, handle mount pin
Pliers, slip-joint
Rags, wiping (item 21, Appendix C)
Punch, straight drive-pin, 1/4-inch
Solvent, drycleaning (item 28, Appendix C)
Punch, straight drive-pin, 1/2-inch
Washer, pivot block-to-pivot control
Threading set, screw
(as required)
Vise, machinists
Wrench, box, 9/16-inch
Personnel Required
Wrench, open-end, 3/4-inch
(two required)
One
Wrench, open-end, 15/16-inch
Equipment Condition
Materials/Parts
Loader control box door removed
Detergent, GP (item 7, Appendix C)
(page 2-1167)
Grease (LO 5-2420-222-12)
Lockwasher, control pivot screw
(two required)
ACTION
LOCATION
ITEM
REMARKS
REMOVAL
1.
Loader backhoe
Right platform
Remove (page 2-2079).
2.
Handle (1) and
Nut (3)
Using 15/16-inch open-end wrench,
handle mount (2)
loosen.
3.
Handle mount (2)
Handle (1)
a.
Note relative position for proper
with assembled parts
placement during installation.
b.
Unscrew and take out.
2-1324
|