TM 5-2420-222-20-1
HAND THROTTLE CABLE
This task covers:
a.
Removal (page 2-322)
e. Repair (page 2-325)
b.
Disassembly (page 2-324)
f.
Assembly (page 2-325)
c.
Cleaning (page 2-324)
g. Installation (page 2-326)
d.
Inspection/Replacement (page 2-325)
INITIAL SETUP
Tools
Materials/Parts - Continued
Caps, vise jaw (pair)
Pin, cotter, cable
Handle, ratchet, 3/8-inch
Pin, cotter, cable swivel
Pliers, slip-joint
Rags, wiping (item 21, Appendix C)
Socket, 3/8-inch drive, 7116-inch
Solvent, drycleaning (item 28, Appendix C)
Socket, 3/8-inch drive, 9/16-inch
Threading set, screw
Personnel Required
Vise, machinist's
Wrench, open-end, 112-inch
One
Materials/Parts
Equipment Condition
Lockwasher, bracket screw
1. Loader control box door removed
Lockwasher, U-bolt nut (four required)
(page 2-1167)
2. Right Inner platform ramp removed
(page 2-1095)
ACTION
LOCATION
ITEM
REMARKS
REMOVAL
1.
Swivel (1) and
Cotter pin (3)
a. Using slip-joint pliers, bend ends
clip (2)
straight and pull out.
b. Get rid of.
2.
Swivel (1), throttle
Clip (2)
Using slip-joint pliers, unsnap from
lever (4) and
cable (5).
cable (5)
3.
Throttle lever (4)
Swivel (1) with
Take out.
and clip (2)
attached cable (5)
4.
Throttle lever (4)
Clip (2)
Take off.