![]() TM9-2320-363-20-2 
C E N T E R GAGE PANEL AND LAMPS REPLACEMENT 
This task covers: 
a. Removal b. Cleaning/Inspection c. Installation 
INITIAL 
SETUP 
Equipment Condition: 
Applicable Configuration: 
M916A1 
Condition Description 
Reference 
Batteries Disconnected 
Page 2-29 
Tools and Special Equipment: 
Shop Equipment, SC 4910-95-CL-A72 
Tool Kit, SC 5180-90-CL-N26 
REMOVAL 
1. 
REMOVE FOUR SCREWS (1) AND PULL PANEL ASSEMBLY (2) AWAY FROM DASHBOARD. 
NOTE 
T a g all plugs, connectors, and g a g e s prior to removal to aid in installation. 
2. 
DISCONNECT THREE PLUGS (3) AND TWO CONNECTORS (4) AND REMOVE PANEL ASSEMBLY 
(2). 
REMOVE FOUR LAMP HOLDERS (5) FROM FOUR GAGES (6, 7, 8, AND 9). 
3. 
4. 
TURN FOUR LAMPS (10) TO LEFT AND REMOVE FROM FOUR LAMP HOLDERS (5). 
REMOVE THREE NUTS (11) AND HARNESS (12) FROM GAGE (9). 
5. 
6. 
REMOVE TWO `NUTS (13), TWO WASHERS (14), BRACKET (15), AND GAGE (9) FROM PANEL (2). 
7. 
REPEAT STEP 6 FOR THREE GAGES (6, 7, AND 8). 
CLEANING/lNSPECTION 
Clean and inspect all parts in accordance with Chapter 2. 
INSTALLATION 
1. 
INSTALL GAGE (9), BRACKET (15), TWO WASHERS (14), AND TWO NUTS (13) ON PANEL (2). 
2. 
REPEAT STEP 1 FOR THREE GAGES (6, 7, AND 8). 
INSTALL HARNESS (12) AND THREE NUTS (11) ON GAGE (9). 
3. 
4. 
INSTALL FOUR LAMPS (10) IN FOUR LAMP HOLDERS (5) AND TURN TO RIGHT. 
 | 
| 
 
 Privacy Statement - Press Release - Copyright Information. - Contact Us  |