TM 9-2320-360-34-1
7-3. TRANSMISSION CONTAINER UNPACKING/PACKING
This task covers:
a. Upper Container Removal
c. Transmission Installation
b. Transmission Removal
d. Upper Container Installation
Initial Setup:
Equipment Conditions
Materials/Parts
Transmission prepared for storage (para 7-4).
Lockwashers (8) (Item 108, Appendix F)
Lockwashers (8) (Item 109, Appendix F)
Tools and Special Tools
Tool Kit, Genl Mech (Item 202, Appendix E)
Sling Assembly (Item 160, Appendix E)
Wrench, Torque, 0-175 Lb-Ft (Item 236,
Appendix E)
a.
Upper Container Removal
(1)
Release air pressure at vent valve (1).
(2)
Remove 22 nuts (2), lockwashers (3), and
screws (4). Discard lockwashers.
WARNING
Keep out from under heavy parts.
Falling parts may cause serious
injury or death to personnel.
(3)
Attach suitable lifting device and remove
upper container (5) from lower container
(6).
Change 1 7-3
|