TM 5-2420-224-20-1
Section
VIII.
PREPARATION
FOR
STORAGE
OR
SHIPMENT
This section describes how to prepare vehicles for temporary storage and remove them from
temporary storage.
NOTE
Vehicles enter storage phases predicated on length of storage period and maintenance
services required.
1. Phase I Preservation Tasks (Up to 30 Days):
a. Place front loader and backhoe (SEE) or forklift and crane (HMMH) in transport position
(TM 5-2420-224-10) with safety valves closed.
b. Retract hydraulic piston rods into cylinders as far as possible. Clean and coat all exposed
portions of attachment cylinders and hydraulic spool valves with solid lubricant preservative
(Appendix C, Item 21). Exposed portions include:
Front loader lift cylinders (SEE)
Forklift lift, tilt, and rotating cylinders (HMMH)
Backhoe dipper, bucket, boom, swing, stabilizer, and tilt cylinders (SEE)
Crane external end extension, inner boom lift, mast locking, outer boom, and outrigger
cylinders (HMMH)
Front loader/forklift control valve spools
Tilt and latch control valve spools
Backhoe control valve spools (SEE)
Crane valve bank spools (HMMH)
c. Coat tools with solid lubricant preservative (Appendix C, Item 21):
Three carbide bits (SEE)
Clay spade (SEE)
Moil point (SEE)
Chisel point (SEE)
Set of impact sockets (HMMH)
48-oz (1.4-kg) hammer
Adjustable wrench
Pinch bar
d. Coat five hydraulic and chassis toolbox hinges with solid lubricant preservative (Appendix
C, Item 21).
e. Add diesel fuel additive (Appendix C, Item 1).
Change 2
|