13-6.
FENDERS AND SUPPORTS MAINTENANCE (Cont).
6.
Install six capscrews (9), washers (10), new lockwashers (11), and nuts (12) in fender (1) and canopy or ROPS
(6).
7.
Install four capscrews (8), washers (13), new lockwashers (14), and nuts (15) in structural frame (16) and fender
brace (5).
8.
Remove lifting device from fender (1).
FOLLOW-ON TASKS:
NOTE
Perform the following only if right fender was removed.
Install loader backhoe control box door (see TM 5-2420-222-20).
Install center platform (see TM 5-2420-222-20). NOTE
NOTE
Perform the following only if left fender was removed.
Install warning alarm wiring harness (see TM 5-2420-222-20).
NOTE
Perform the following if right or left fender was removed.
Install stoplight wiring harness (see TM 5-2420-222-20).
Install rear light wiring harness (see TM 5-2420-222-20).
Install combined tail and floodlight (see TM 5-2420-222-20).
Install combined tail and stoplight (see TM 5-2420-222-20).
Install loader backhoe control guards (see TM 5-2420-222-20).