CYLINDER LINERS REPLACEMENT - CONTINUED
0245 02
PROJECTION CHECK
NOTE
Correct cylinder liner projection is necessary to prevent leaks between cylinder liner, cylinder head and cyl-
inder block.
1.
Remove any nicks from cylinder liner counterbores on
top of cylinder block (2) with emery cloth.
6
2.
Install new cylinder liners (1) into cylinder block (2),
without gaskets and preformed packings.
5
3.
Install new spacer plate gasket (5) and spacer plate (6).
1
2
421-0018
NOTE
Tighten capscrews in sequence specified in WP 0025 00.
4.
Install 36 (6 for each cylinder) flat washers (7) (Item
185, WP 0250 00), washers (8) (Item 184, WP 0250
10
9
screws (10) (Item 176, WP 0250 00), as shown in
8
7
illustration, to seat cylinder liners (1) in cylinder block
1
(2). Tighten capscrews evenly to 35 lb-ft (47 Nm) and
then to 70 lb-ft (95 Nm).
2
421-0019
Change 1
0245 02-4
|