TM 5-2410-233-23
GROUND HANDLING PROCEDURES - CONTINUED
0178 00
OPERATING/ADJUSTING HYDRAULIC JACK STANDS - CONTINUED
1.
Assemble hydraulic jack stands as follows:
a.
Install extension tube (1) and collar (2) on jack
4
8
stand (3).
1
b.
Install hydraulic cylinder (4) in jack stand (3)
and under tab of collar (2).
2
c.
Repeat steps a and b for other jack stand (3).
d.
Connect hydraulic lines (5) from throttle valves
to each hydraulic cylinder (4).
e.
Connect hose (6) from valve tee to hydraulic
pump.
7
f.
Open both throttle valves and control valve on
hydraulic pump and ensure cylinders (4) are fully
retracted. If necessary, push down on extension
3
3
tube (1).
THROTTLE
5
VALVES
6
WARNING
Ensure all jack stands and blocking are prop-
erly placed and secure, to prevent movement of
item to be lifted. Failure to follow this precau-
tion could result in serious injury or death.
CONTROL
VALVE
HYDRAULIC PUMP
386-679
2.
Put jack stand under area to be lifted. Ensure lifting point is sturdy.
JACKING POINT
RIGHT SIDE REAR.
LEFT SIDE IS THE SAME
386-813
0178 00-2
|