LOADER BUCKET LEVEL INDICATOR
This task covers:
a.
Removal (page 2-1838)
d.
Installation (page 2-1841)
b.
Cleaning (page 2-1840)
e.
Adjustment (page 2-1842)
c.
Inspection/Replacement (page 2-1840)
INITIAL SETUP
Tools
Materials/Parts
Driftpin, brass-tipped, 3/4-inch
Lockwasher (two required)
Hammer, cross-peen, 3-pound head
Rags, wiping (item 21, Appendix C)
Handle, ratchet, 1/2-inch drive
Solvent, drycleaning (item 28, Appendix C)
Lifting equipment, 1000-pound
capacity
Personnel Required
Pliers, retaining ring
Socket, 1/2-inch drive, 9/16-inch
Two
Wrench, open-end, 11/16-inch
ACTION
LOCATION
ITEM
REMARKS
REMOVAL
1.
Bucket indicator
Nut (2)
a.
Note number of exposed threads on
rod (1)
rod (1).
b.
Using 11/16-inch open-end wrench,
unscrew and take off.
2.
Indicator pivot (3)
Bucket indicator
Pull out.
rod (1) with
assembled nut (4)
3.
Bucket indicator
Nut (4)
Unscrew and take off.
rod (1)
4.
Indicator guide
Bucket indicator
Pull out.
tube (5)
rod (1)
5.
Indicator guide
Two screws (7) and
a.
Using 9/16-inch, 1/2-inch drive socket
tube (5) and loader
lockwashers (8)
and ratchet handle, unscrew and take
bucket cylinder
out.
head (6)
b.
Get rid of lockwashers (8).