TM 5-2420-222-20-3
LOADER CONTROL VALVE-TO-LOADER BUCKET CYLINDER ROD END OIL LINES - CONTINUED
ACTION
LOCATION
ITEM
REMARKS
INSTALLATION - CONTINUED
25.
Special
Oil Line (2)
a.
Uncap connector (7).
connector (1)
b.
Unplug.
c.
Take off tag.
d.
Screw on and tighten using 1-inch
and 1 1/4-inch open-end wrenches.
26.
Elbow (3)
Oil line (4)
Using 1-inch and 1 1/16-inch open-end
wrenches, tighten.
27.
Tee (5)
Two hoses
a.
Uncap hose (1 or 9) if removed for
(6 and 7)
access.
b.
Take off tags.
c.
Screw in and tighten using 7/8-inch
and 1-inch open-end wrenches.
NOTE
If installing loader control valve-to-right loader bucket cylinder oil line, skip steps 28 thru 30.
28.
Left side
Four hoses (9, 10,
Place in same relative position noted
frame (8)
11.and 12), clamp
during removal.
(13), and spacer (14)
29.
Left side frame
Screw (15) and new
Screw in and tighten using 9/16-inch,
(1), clamp (13),
lockwasher (16)
3/8-inch drive socket and ratchet
and spacer (14)
handle.
30.
Four hoses (9, 10,
Take off tags.
11, and 12)
31.
Adapter (17)
New packing (18)
Place in position.
32.
Loader bucket
Adapter (17)
a.
Unplug cylinder (19).
cylinder (19)
b.
Screw in and tighten using 1-inch
33.
Adapter (17)
Oil line (20)
a.
Take off tag.
b.
Screw in and tighten using 7/8-inch
open-end wrench.
34.
Loader bucket
Two clamps
a.
Place in same relative position noted
cylinder (19), and
(22 and 23)
during removal.
two oil lines
b.
Using 1/4-inch flat-tip screwdriver,
(20 and 21)
tighten.
2-1676
|